Buildings nearing completion
Nov 9, 2016
Progress update.
Work continues on multiple buildings and a few are now receiving their final touches.
Finishing work is ongoing in the Gallery Building’s (G02) Cryogenics Office, which will be one of the first occupied work spaces in the facility. The Cryo-Compressor Building (G04) was prepared to give ESS partial access to the gas storage area this week. Roof works are nearing completion on the Central Utility Building (H01), and a new permanent road has received its first layer of asphalt, running between the Gallery Building and the Cryo-Compressor Building.
Facade work for G02 Klystron Building and below more of completed G04 Cryo Compressor building.
Walls getting up for H01 CUB Bldg.